Part I of this topic (in the July 2009 edition of Wind Directions) was focused on wind farm design from the point of view of the physical parameters influencing its design: the resource, visual influence, noise and turbine loads. In Part II, the “hardware” aspects of infrastructures (split between civil works, electrical works and the control system (SCADA), construction issues, and commissioning, operation and maintenance), are described.
ELECTRICAL WORKS
The turbine generator is low voltage (usually below 1 kV, exceptionally 3 kV, and often 690 V). This voltage level is not high enough for direct interconnection to other turbines. Therefore, it is necessary for each turbine to have a transformer to step up to Medium Voltage (MV - 10 to 35 kV). In most cases, turbines are interconnected by
underground cables. The design requirements for the wind farm electrical system are set out in the connection agreement, a ‘grid code’ or something similar.
• meet local electrical safety requirements and be capable of being operated safely;
• achieve an optimum balance between capital and operating costs (electrical losses) and reliability;
ensure that the wind farm satisfies the technical requirements of the electricity network operator; and
• ensure that the electrical requirements of the turbines are met.
SCADA AND INSTRUMENTS
to determine what corrective action, if any, needs to be taken. It also records energy output, availability and error signals, which will act as a basis for any warranty calculations and claims. The SCADA system also has to implement any requirements in response to instructions from the network operator.
be some variable costs associated with the civil works which are small compared to the cost of the project as a whole. The construction time is also very short, as a 10 MW wind farm can easily be built within a couple of months.
commercial operation; that means the availability will increase from 80-90% after commissioning to the long-term level, on average, of 97% or more. Once a wind farm is working, usually 40 hours per year per turbine have to be budgeted for routine maintenance work, which is usually covered by a two- to five-year warranty from the turbine supplier.
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.